Plan tab

What was agreed. The contract and requirements basis, scope and traceability, SOW terms, BRD amendments, and the timeline.

The Plan tab shows what was agreed with the client. It shows approved state only. The plan changes through reviewed changes: new sources come in through Sync on Events, and you add a change by hand with Stage a change. To work the plan day to day, use Items.

Plan has two parts:

  • Scope (named for the kind: Scope on an Implementation, Deliverables on an Advisory, Service on a Managed service).
  • Timeline.

Scope

The basis

The top row says what the plan rests on:

  • the contract: the effective SOW, or No signed SOW yet,
  • the requirements basis: the BRD, or No BRD recorded.

Each has Open to read the document.

The delivery plan

On an Implementation, the list is the Delivery plan: a traceability list from each requirement to the deliverables that cover it and the test cases that test it. Switch between By requirement and By deliverable.

On an Advisory or Managed service, which have no requirement traceability, the list shows the deliverables instead.

Gaps are listed above it as one line of filters, for example "Gaps: 33 requirements have no deliverable · 1 milestone is overdue". Click a gap to filter the list to it. The gap filters are:

  • No deliverable: a requirement no deliverable covers.
  • No test case: a requirement with no test case.
  • No due date: a deliverable or milestone with no date.
  • Overdue milestone.

At the bottom: Not covered by a deliverable, Test cases with no requirement, and the cancelled and retired items, behind Show cancelled and Show retired.

Click any row to open it in the item pane.

Stage a change

The Stage a change menu offers what the plan holds: Requirement, Deliverable, Milestone, Decision, Test case and Meeting. A deliverable or milestone from the signed SOW is marked "Comes from the signed SOW or a change order": it changes only through a signed change order.

A pending link ("N on Project →") in the header goes to the rows waiting on Events. Review happens only there.

SOW terms, working agreements and BRD amendments

  • SOW terms: the scope and commercial terms from the signed SOW. "They change only by a signed change order." Before signing, "They become the baseline when the SOW is signed."
  • Working agreements: agreements made during the project, such as cadence, communication and contacts.
  • BRD amendments: every requirement that changed since the BRD was signed, with its status: Open, In the signed BRD, Superseded or Withdrawn. When nothing changed: "No requirement has changed since sign-off."

The build product

On an Advisory or Managed service, Scope also shows the build product: the BRD and its hand-off, or the inherited blueprint.

Phase template

While the project has no milestones, a line offers the kind's phase template, for example Use the Implementation phase template. It stages the default milestones for review on Events. See Project kinds.

Timeline

Timeline is the calendar of the project's milestones, deliverables and meetings. From here you can Stage a change and edit a planned meeting. Show cancelled milestones lists milestones taken out of the plan, which you can still open.

To see the work under each milestone, use Items › Work.